INSTALL LANES & DAILY STAGING
Lane Structure
- Monday Lane A + B Groups
- Tuesday Lane A + B Groups
- Wednesday Lane A + B Groups
- Thursday Lane A + B Groups
- Friday Lane A + B Groups
EXAMPLE: Only Team A has a scheduled install on Monday
Both teams run installs Tuesday–Friday
“Lane A + B Groups” = two install lanes (or crews) operating per team
🗓️ HVAC Install Schedule (Team A & B)
Monday
Team A
- Lane A Group: Full install job (Primary scheduled project)
- Lane B Group:
- Assist on main install or
- Handle prep work (duct, materials staging, permits, partial jobs)
Team B
Punch list or small carryover jobs
No full installs scheduled
Focus on:
Equipment/material prep for week
Warehouse organization
Truck restocking
Training / ride-alongs
Daily Process
- Assign job to lane
- Place job folder
- Attach checklist
- Stage materials
Crews must sign checklist before loading.
WAREHOUSE & INVENTORY MANAGEMENT
Weekly Inventory Control
- Maintain master inventory list
- Track usage
- Identify shortages
Ordering System
- Review Thursdays
- Order Friday weekly
- Verify deliveries
Standard Stock Categories
- Install materials
- Service parts
- Filters/cleaners
- PPE
- Consumables