DUCT SYSTEM INSTALLATION PROCESS

This document defines the standard scope of work and quality expectations for duct system projects. Scope may include full duct replacement, partial replacement, or duct-only upgrades using existing components.

Keating Kuhn

Keating Kuhn

January 8, 2026

VERIFY APPROVED SCOPE OF WORK ON INVOICE BEFORE DOING ANY DEMOLITION

SITE PREP & HOME PROTECTION

  • Enter home respectfully and review work areas with homeowner
  • Lay floor protection from entry to attic access
  • Lay plastic sheets under all supply and return buckets
  • Protect furnishings and fixtures as needed

* When job scope requires removal of supply grilles, apply green painter’s tape over drywall buckets to prevent debris from entering the home *


ATTIC – DEMO PHASE

  • Remove ductwork, connectors, buckets, plenums, and collars per scope
  • Double-bag all fiberglass/porous debris before bringing it out of attic
  • Place all trash behind vehicle in driveway ON PLASTIC

PLENUM & COLLAR INSTALLATION

METAL PLENUM

  • All seams mechanically fastened before sealing
  • Insulate plenum outside before bringing it into the attic
  • Plenum must be square, level, and fully supported (not hanging on the unit)
  • Cut collar holes clean and correctly sized
  • Install collars tight to plenum with mastic and screws
  • All dampers must be installed blade lined up with the airflow (no scoop)
  • Seal all seams, corners, and joints with mastic
  • Seal collar-to-plenum connections fully
  • Reinforce mastic with approved foil tape after curing
  • Dampers accessible and adjustable after installation

DUCT-BOARD PLENUM

  • Cut ductboard square and to proper dimensions
  • Assemble plenum with correct fold and closure method
  • Plenum must be level and independently supported
  • Cut collar openings clean and precise
  • Insert collar fully and flush with duct-board surface with tabs
  • Seal collar-to-ductboard connections completely
  • All dampers must be installed blade lined up with the airflow (no scoop)
  • Seal all duct-board seams with mastic
  • Dampers accessible and adjustable after installation

BUCKET REPLACEMENT

  • Verify bucket size matches grille and airflow design
  • Bucket must fit snugly in drywall opening
  • If enlarging drywall opening:
    • Lay plastic sheeting below opening
    • Helper must be positioned below with a box to catch dust
  • Apply thin bead of spray foam or thick bead of mastic between bucket and drywall
  • Hold bucket from attic while helper installs and aligns grille from below
  • Ensure grille sits flat and centered

*Do not use silicon on grille/drywall connection*


DUCT INSTALLATION

  • Run new flex duct per Manual D
  • Avoid sharp bends, compression, and excess length
  • Strap and space ductwork to prevent sagging per best practice

SYSTEM COMMISSIONING & FINAL CHECKS

  • Verify airflow at each register
  • Adjust dampers as needed
  • Check static pressure (target within manufacturer tolerance)
  • Verify system operation:
    • Heating and cooling performance
    • Temperature split
    • Air delivery (CFM intent)
  • Document final readings
  • Walk homeowner through completed work and improvements

INSTALLER ACCOUNTABILITY

  • Only perform work included in the approved scope
  • Photos, notes, and readings must be documented in Workiz
  • Job is not complete until commissioning and homeowner walkthrough are finished